Anchor | ||||
---|---|---|---|---|
|
To ignore schedule dependencies:
In
...
Automation Desk,
...
in the left navigation pane, click Monitor >Jobs/Events.
...
You see the Monitor Workspace.
Click the double arrow to the right of the workspace to open the Search dialog box.
To view all processes (completed and waiting), click to select Scheduled Start Date Time. Select the date and time and any other required search criteria, and click the green Search button.
Click a scheduled event in Waiting status
...
.
...
Click OK in the confirmation dialog box.
...
Click Ignore Dependencies on the ribbon. Or, you can right click the event and select Ignore Dependencies from the menu. You can also choose to cancel any Waiting event by selecting Cancel.
Click the Refresh drop down and select Screen to see the latest event status
...
.
...
To export the data displayed in the workspace, click the Distribution drop down, click Export and select the file format.