Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

For example, the following figure shows the Reason Code based Start comment for an entity that was added to the composite as of 1/1/1980, but was Approved with an Effective Date of 1/4/1980.

Reason Code Comments (Monthly Mode)Image Modified

IMPORTANT:

  • Eagle strongly recommends that once you select the Performance System Parameter option, it must not be changed and must be applied to all Performance Composites.
  • All pending records must be in Approved status prior to implementing the 9.1 version of Composite Approval.
  • Eagle strongly recommends that the 10.0 version of Composite Approval be implemented at the start of a new month.

...

Info
The Approval report does not recognize membership changes that were entered manually through the Performance Composite entity screen.


Pending Record Warning MessageImage Modified