Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  1. In Accounting Center, in the left navigation pane, click Setup Fund Accounting Distribution Schedules > Edit Distribution Schedule.
    You see the Edit Distribution Schedule panel.
  2. Complete the options on the Edit Distribution Schedule panel.
    You must specify the entity, along with the Begin Date and End Date field values to include schedules within a date range.
  3. Click Submit.
    You see a list of distribution schedules that met your criteria in the Show All tab..
  4. Select the check box for each distribution schedule that you want to change and click Change Distribution Schedule.
    You see a row for each distribution schedule you selected for updates in the Change Distribution Schedule grid.
  5. Select each distribution schedule you want to change and edit the information for that schedule.
  6. Click Submit.