- From the Performance Center window, click the Performance Desk and click Commit Journal in the left navigation.
You see the Commit Journal workspace displaying a list of available views in the right navigation. - Select a view and click Submit View on the ribbon. Or, double click the view.
You see the selected view in the workspace. - Click View/Download on the ribbon and then select Calculation Results or Calculation Results for This Entity.
You see the underlying performance calculation results in a new workspace. - Select a cell you wish to change and right click to view the Maintain Data options.
Options include:
– Add Security Position
– Edit Security Position
– Edit Performance Returns
– Performance Returns Maintenance Journal
– Go to Cash Activity Maintenance - To add a security position select Add Security Position.
You see the Add Security Position dialog box. - Enter security and other data in the appropriate fields as needed.
- To edit a security position select Edit Security Position.
You see the Edit Security Position dialog box. - Select a security and make changes to the appropriate fields as needed.
- To make changes to an existing value select Edit Performance Returns.
You see the Edit dialog box showing the Existing Value and a blank field for New Value. - Enter a New Value.
- Click Save.
You see the changes in the cell, which is now highlighted to show that it has been changed.
Anchor |
---|
| commit_journal_monitor_and_chang_3281 |
---|
| commit_journal_monitor_and_chang_3281 |
---|
|
Anchor |
---|
| _Toc420668625 |
---|
| _Toc420668625 |
---|
|
Client Side CommitThe Client Side Commit process allows you to manually commit changed performance calculation results to the database.
...
- From the Performance Center window, click the Performance Desk and click Commit Journal in the left navigation.
You see the Commit Journal workspace displaying a list of available views in the right navigation. - Select a view and click Submit View on the ribbon. Or, double click the view.
You see the selected view in the workspace. - Click View/Download on the ribbon and then select Calculation Results or Calculation Results for This Entity.
You see the underlying performance calculation results. - Edit underlying data as needed. See "Edit Performance Returns."
- Click Client Side Commit on the ribbon. Or, right click and select Client Side Commit.
You see the Commit Options dialog box. - Select one or more Entities by using the Entity Selector.
- Select whether you wish to calculate to-date returns, Yes or No.
- If you selected Yes, specify the returns you wish to commit.
Options include:
– Year End
– Quarter End\
– Month End
– Use the Business Calendar - Select Additional Options as necessary.
- Select the Commit Source.
- Click Publish.
- You see a message confirming the action.
Anchor |
---|
| commit_journal_monitor_and_chang_1361 |
---|
| commit_journal_monitor_and_chang_1361 |
---|
|
Anchor |
---|
| _Toc420668626 |
---|
| _Toc420668626 |
---|
|
Resubmit Performance CalculationAfter you make changes or additions to Performance returns, you must resubmit the Performance Calculation report in order for the scrubbed records to be picked up.
...
- After editing a return, select the row you want to resubmit.
- Select Resubmit Performance Calculation on the ribbon and then select it again from the menu.
You see a message confirming that the report was submitted successfully.
Anchor |
---|
| commit_journal_monitor_and_chang_1025 |
---|
| commit_journal_monitor_and_chang_1025 |
---|
|
Anchor |
---|
| _Toc420668627 |
---|
| _Toc420668627 |
---|
|
Resubmit Calculation with OverrideThe Resubmit Calculation with Override option allows you to resubmit performance calculation data with different parameters without first needing to download return results. You can enter values that temporarily override the options associated with the report profile and its assigned report rule. You can select dates and entities, report rule, field rule, benchmarks, and commit options.
...